This project involved the supply and installation of 146 steel tube piles as part of the expansion of the Able Point Marina.
It was necessary to carefully program the work due to the shallow water conditions which existed prior to dredging.

The works included:

  • Supply and installation of 146 no. 508 mm diameter steel tube piles of wall thickness varying from 9.5-17mm in lengths up to 18m.
  • Splicing of 146 steel tube piles to make up the 18 m driving length.
  • Supply and installation of 146 no. HDPE sleeves to each pile.