Overseas Passenger Terminal Extension - Circular Quay

Client: Port Authority of NSW
Capabilities: Construction, Sheet Piling
Region: Circular Quay (New South Wales)
Completed: November 2014

The $14.6m project increased the berthing length of the Overseas Passenger Terminal wharf by 60 metres as well as providing a mooring dolphin to assist passenger ships berthing at Circular Quay, Sydney Harbour.

Construction works were undertaken whilst the Terminal remained operational, with ships berthing alongside.

Waterway Constructions utilised both land-based and marine based plant to expedite the program.

The scope of works included:

  • 72 metres sheet pile wall
  • 28 x vertical and 8 x 1:3 raked 610mm diameter tubular pile wharf installation
  • 4 x 1:6 raked 1200mm diameter dolphin pile installation
  • 11 x Pre-cast concrete headstocks and 94 x infill panels
  • 14 x ground anchors drilled through piles
  • Construction of 6m diameter x 3m deep circular mooring dolphin
  • 250 cubic metre insitu concrete deck pour
  • 1200 tonne of rock backfill
  • Over 4000 anodes (cathodic protection)
  • Placement of scour protection
  • Commercial diving works
  • Marine plant, craneageand vessel operations
  • Fender installations
  • Electrical works
  • Seabed profiling
Overseas Passenger Terminal Extension - Circular Quay