Caltex Kurnell Wharf Upgrade

Client: Caltex Australia
Capabilities: Construction, Piling
Region: Sydney (New South Wales)
Completed: August 2015

The existing jetty was upgraded to allow for the berthing and mooring of vessels up to 100,000 tonne. To achieve this, three new dolphins were installed with quick release hooks and fenders. Painted steel catwalks leading out to each of the dolphins were installed with handrail, ladders and light poles. Summary of scope items:

  • Supply and install 27 off 1200mm dia with 25mm wall thickness piles
  • Precast shells formed and poured offsite and transported by barge- maximum lift 85 tonne
  • Supply and install 7.5 x 7.5m ; 11 x 10m ; and 7 x 10m concrete dolphins
  • Supply and install 6 new quick release hooks
  • Supply and install 2 new SCN 1800 Fenders